Image

Thursday, October 30, 2014

Continuing Update - Gas Plant Construction Project

Hansa Meyer Global Transport's Houston Team has had a very busy summer managing the heavy hauls and barges for a gas plant construction project in US.  Scroll down through the blog site to find several related articles.  The hard work is paying off as barge number 1 made the landing this week after a river journey of nearly 2,000 miles. With the barge site secure and the bridges in place, the equipment roll-off is underway.  In the meantime, barges 2 & 3 have been loaded and have launched as well.


After nearly 2,000 miles the first of 3 barges pushes its way to the landing.


Looking from the stern towards the riverbank, a beautiful fall morning for a roll-off.


First piece to roll-off at the barge site that Hansa Meyer was commissioned to improve and make ready.

Roll-off from the barge site will continue for approximately three days.
The sequencing, scheduling and delivery of the equipment was tightly controlled by the team as many of the pieces were transported directly under hook for immediate positioning within plant.  With barge number 1 on site and getting unloaded, barge numbers 2 & 3 are not far behind.  Having only days between landings, the loading and departures on the following barges had to well planned and executed.

Barge number 2 loading out with more towers and processing skids

Every piece of equipment has had hours of transport engineering and planning before being loaded 

Barge number 2 leaving the port on its way to the plant site nearly 2,000 miles up river

Barge number 3 being loaded with one of the heavier pieces for this transport

Barge number 3 pushing out of the port.
Check back periodically for more updates on this project and others.  The team at Hansa Meyer Global Transport greatly appreciates our customers and the opportunities to work with them on so many amazing projects.  We also enjoy sharing our stories with you.  Your comments are welcomed and thanks for stopping at our site.


Monday, October 13, 2014

Layout, Load Out, and Launch - Barge #1

The Hansa Meyer Global US team introduced a 2014 LNG Plant Construction project to our blog followers back in April.  It has been a busy summer for the team managing the consolidation of complex heavy loads from multiple domestic origins to the Port of Houston.  This project update, as the title hints covers the layout, load out, and launch of the first of three barges that will make their way through the Intracoastal Waterway to the site.
As they say, "Measure Twice, Cut Once" our staff engineer developed the complex layout drawings.
Stands and Beams are placed on the deck according to the plan
While not the most fun to watch, the pre-load work is critical to the success of the project.  Much time and effort goes into layout designs that consider weight distribution, balancing, as well as offloading, before the first piece of equipment is loaded on the deck.  For this load 56 stands will be positioned bridged by 28 beams, with 76 welded D-rings and chain tensioners to lock the equipment into place.  But then the fun starts with ten pieces of equipment positioned to load on the barge with a combined weight of over 1.6 million pounds!





Activity in the port doesn't stop after the sun goes down.  With the help of flood lights the loading continues to ensure meeting the departure window.






With the Hansa Meyer Global Transport banner in place, the barge is ready to take the project equipment on a 2,000 mile voyage through America's Intracoastal Waterway.




One last picture as the 260' x 75' barge is pushed up river by an 1,800 horse power, steel tug, carrying 14,000 gallons of fuel. Bon Voyage...


Stay tuned as we have on-going civil work on site as well as two more barges to load.  We appreciate you reading our blog.  You comments are welcomed below.