Image

Monday, April 21, 2014

US - Project - LNG Plant Equipment - Part 3 - Bird's Eye View

Hansa Meyer Global Transport’s Houston office is managing multiple origin moves as part of a US east coast LNG project.  Due to the timing of the project, there is a need for a regional storage solution with scheduled delivery to the job site.  When Hansa Meyer's Houston team keeps an eye on a project, they mean it !  Below are some offload pictures to the storage site and then an ariel view taken while circling in a private plane.  Needless to say, this project is off to a flying start !

Offload from trailer in to the storage facility

Setting equipment into place

Wing-tip view of our equipment placed in the right side of the yard

Bird's eye view - - 

This project is off to a flying start !!

Saturday, April 12, 2014

148,810 lbs -- Very Im-press-ive

Hansa Meyer Global Transport's US team successfully completed delivery of a 350 ton servo press to its new home in Tennessee.  The part pictured below is part of the press weighing 148,810lbs. The team met the piece in Charleston, SC, secured it to the 13 axel heavy-haul trailer, and inspected the load before sending it on a 400+ mile trip.
Preparing to remove the press from the mafi trailer at the Port of Charleston

Loading the trailer for the over-road-leg of the shipment

Load secured with multiple chains and tie-downs

Impressive load on its way to Tennessee

The journey to Tennessee was eventless and the press was successfully delivered on April 3, 2014.  The customer was very pleased with the project and thanked the team for all the hard work and attention.

Friday, April 11, 2014

US - Project - LNG Plant Equipment - Part 1

In early April 2014 Hansa Meyer Global Transport’s Houston office kicked off a project handling newly fabricated equipment for an LNG construction project on the east coast of the United States.  The project will consist of 59 specific pieces weighing approximately 16,000 frt in total.  The entire project will consist of rigging and take away from multiple origins, consolidation and temporary equipment storage, barging and permitted truckload moves including several super loads, and final destination delivery and offloading. The first piece to move was a deethanizer tower as seen below. 
136 ' long deethanizer tower weighing approximately 433,000lbs
Positioning the SPMT to pull tower out of the fabrication bay
Moving the tower to a temporary staging location
The column was moved from the bay and positioned on stands and beams to hold in place while the second matching tower was moved into the bay for fabrication.  Once completed the columns will be moved to the barge site, loaded and begin the leg to the construction site.

US - Project - LNG Plant Equipment - Part 2

Read more about this on-going project in the blog "US-Project-LNG Plant Equipment-Part 1" 

Hansa Meyer Global Transport’s Houston office is managing multiple origin moves as part of this US east coast LNG project.  The pictures below show the first of 21 pieces of equipment being fabricated at this southwest plant. The propane refrigeration condenser pictured below is one of nine that will be manufactured in the coming weeks.

Using overhead crane equipment to position unit on to trailer

56'L x 16'W x 14'H & weighing approximately 58,000lbs

Two units were transported out to make room for the next pair to be made

Final inspection before heading across country to the project