Some of you read our blog earlier this year about Hansa Meyer moving two reactors from Asia to Texas. Picking up where we left off, Hansa Meyer was back on site to move the reactor to its final pad location. Weighing 186,512 lbs, Hansa Meyer used owned equipment including our 500-ton Hydra-Slide to set the reactor in place. Our rigging teams and operators are excellent having completed multiple jack and slide operations this year. We appreciate their hard work, and you, for taking time to read about our projects.
As always, thank you for reading our blog and we welcome any comments.
Using the 500-ton Hydra-Slide to slide the reactor |
Rotating the reactor on a 300-ton turn table to correct orientation |
Final set onto the pad |
As always, thank you for reading our blog and we welcome any comments.